Commissioning Dashboard
4 Brandon Road - Digital FAT/SAT Tracking & Witnessing
Total Devices
105
DIR entries
Total Points
1,542
Data points
FAT Progress
0%
Factory acceptance
SAT Progress
0%
Site acceptance
CBN Onboarded
0%
Network ready
Sub-Systems
FAT Status
0%Complete
SAT Status
0%Complete
CBN Onboarded
0%Complete
Commissioning Programme
Commissioning Programme
25 Feb 2026 → 22 Jun 2026
52%
Programme Progress
FAT Complete
30 Apr 2026
All sub-systems
4days
Power On
05 May 2026
9days
MSI Site SAT
01 Jun 2026 → 19 Jun 2026
15 days
36days
Practical Completion
22 Jun 2026
57days
Key Milestones
Programme Start
25 Feb 2026
major✓
FAT Complete (All Sub-Systems)
30 Apr 2026
critical
4days
Power On
05 May 2026
critical
9days
BMS Testing Starts
11 May 2026
major
15days
MSI Site SAT Starts
01 Jun 2026
critical
36days
Sub-Systems Integration
01 Jun 2026
major
36days
MSI Site SAT Complete
19 Jun 2026
critical
54days
Practical Completion
22 Jun 2026
critical
57days
Sub-System Integration
BMS System29d
Upcoming
11 May 202619 Jun 2026
Fire Alarm System15d
Upcoming
01 Jun 202619 Jun 2026
Security/Access Control15d
Upcoming
01 Jun 202619 Jun 2026
Lighting Controls15d
Upcoming
01 Jun 202619 Jun 2026
Metering Integration15d
Upcoming
01 Jun 202619 Jun 2026
Integration Requirements Tracker
Integration Requirements Tracker
Outstanding information required from trades for network integration
9
Received
22
Outstanding
31
Total