Commissioning Dashboard

4 Brandon Road - Digital FAT/SAT Tracking & Witnessing

Total Devices
105
DIR entries
Total Points
1,542
Data points
FAT Progress
0%
Factory acceptance
SAT Progress
0%
Site acceptance
CBN Onboarded
0%
Network ready

Sub-Systems

FAT Status

0%Complete

SAT Status

0%Complete

CBN Onboarded

0%Complete

Commissioning Programme

Commissioning Programme

25 Feb 202622 Jun 2026

52%
Programme Progress
FAT Complete
30 Apr 2026
All sub-systems
4days
Power On
05 May 2026
9days
MSI Site SAT
01 Jun 202619 Jun 2026
15 days
36days
Practical Completion
22 Jun 2026
57days

Key Milestones

Programme Start
25 Feb 2026
major
FAT Complete (All Sub-Systems)
30 Apr 2026
critical
4days
Power On
05 May 2026
critical
9days
BMS Testing Starts
11 May 2026
major
15days
MSI Site SAT Starts
01 Jun 2026
critical
36days
Sub-Systems Integration
01 Jun 2026
major
36days
MSI Site SAT Complete
19 Jun 2026
critical
54days
Practical Completion
22 Jun 2026
critical
57days

Sub-System Integration

BMS System29d
Upcoming
11 May 202619 Jun 2026
Fire Alarm System15d
Upcoming
01 Jun 202619 Jun 2026
Security/Access Control15d
Upcoming
01 Jun 202619 Jun 2026
Lighting Controls15d
Upcoming
01 Jun 202619 Jun 2026
Metering Integration15d
Upcoming
01 Jun 202619 Jun 2026

Integration Requirements Tracker

Integration Requirements Tracker

Outstanding information required from trades for network integration

9
Received
22
Outstanding
31
Total

Systems Overview

Sub-SystemDevicesPointsFAT ProgressSAT ProgressCBN Status
BMS
63580/60/60/6View →
Metering
971,0800/970/970/97View →
Security
21040/20/20/2View →
Fire
-0---View →
Lighting
-0---View →