Witnessing

Formal witnessing sessions for FAT, SAT, and handover milestones

FAT Witnessed
0 / 12
10% minimum required
SAT Witnessed
0 / 105
All devices required
Sub-Systems
3
Requiring witnessing
Pending
105
Devices awaiting SAT

MSI Witnessing Requirements

FAT Witnessing

  • Client representative must witness 10% minimum of FAT tests
  • All critical devices require witnessed FAT
  • Photo/video documentation required
  • Sign-off sheet must be completed

SAT Witnessing

  • All sub-systems require witnessed SAT
  • Integration testing with live building services
  • Snagging list generation and tracking
  • Client sign-off before handover progression

Witnessing by Sub-System

Sub-SystemDevicesFAT RequiredFAT CompleteSAT CompleteStatus
BMS
6100 / 6Not Started
Metering
971000 / 97Not Started
Security
2100 / 2Not Started