Witnessing & Handover
Formal witnessing sessions, completion tracking, and handover package preparation
MSI Site SAT Window
01 Jun 2026 → 19 Jun 2026
15 days · PC: 22 Jun 2026
36days
Handover Readiness
0%
Ready
FAT Complete0/105 (0%)
SAT Complete0/105 (0%)
CBN Onboarded0/105 (0%)
Points Verified0/1542 (0%)
FAT Witnessed
0 / 12
10% minimum required
SAT Witnessed
0 / 105
All devices required
CBN Onboarded
0 / 105
Network integration
Docs Ready
2 / 10
Handover documents
MSI Witnessing Requirements
FAT Witnessing
- •Client representative must witness 10% minimum of FAT tests
- •All critical devices require witnessed FAT
- •Photo/video documentation required
- •Sign-off sheet must be completed
SAT Witnessing
- •All sub-systems require witnessed SAT
- •Integration testing with live building services
- •Snagging list generation and tracking
- •Client sign-off before handover progression
Sub-System Status
| Sub-System | Devices | FAT | SAT | CBN | Status |
|---|---|---|---|---|---|
BMS | 6 | 0/6 | 0/6 | 0/6 | Not Started |
Metering | 97 | 0/97 | 0/97 | 0/97 | Not Started |
Security | 2 | 0/2 | 0/2 | 0/2 | Not Started |
Handover Documentation
Device Information Register (DIR)Required
CompletePoints RegisterRequired
Complete!
FAT CertificatesRequiredSAT CertificatesRequired
PendingNetwork DiagramsRequired
PendingSecurity Audit ReportRequired
PendingO&M ManualsRequired
PendingTraining Records
PendingAs-Built DrawingsRequired
PendingWarranty DocumentsRequired
PendingExport Handover Package
Full DIR Export
Complete Device Information Register with all fields and status
Click to generate →
Points Register
Complete points list with nomenclature and verification status
Click to generate →
Complete Package
Full handover package with DIR, points, and certificates
Click to generate →