Handover

Digital handover package preparation and export

Handover Readiness

0%
Ready
FAT Complete0/105 (0%)
SAT Complete0/105 (0%)
CBN Onboarded0/105 (0%)
Points Verified0/1542 (0%)
105
Devices
1,542
Points
0
CBN Onboarded
2/10
Docs Ready

Sub-System Handover Status

BMS
In Progress
Devices6
FAT Complete0/6
SAT Complete0/6
CBN Onboarded0/6
Metering
In Progress
Devices97
FAT Complete0/97
SAT Complete0/97
CBN Onboarded0/97
Security
In Progress
Devices2
FAT Complete0/2
SAT Complete0/2
CBN Onboarded0/2

Handover Documentation

Device Information Register (DIR)Required
Complete
Points RegisterRequired
Complete
!
FAT CertificatesRequired
Partial
SAT CertificatesRequired
Pending
Network DiagramsRequired
Pending
Security Audit ReportRequired
Pending
O&M ManualsRequired
Pending
Training Records
Pending
As-Built DrawingsRequired
Pending
Warranty DocumentsRequired
Pending