Handover
Digital handover package preparation and export
Handover Readiness
0%
Ready
FAT Complete0/105 (0%)
SAT Complete0/105 (0%)
CBN Onboarded0/105 (0%)
Points Verified0/1542 (0%)
105
Devices
1,542
Points
0
CBN Onboarded
2/10
Docs Ready
Sub-System Handover Status
BMS
In ProgressDevices6
FAT Complete0/6
SAT Complete0/6
CBN Onboarded0/6
Metering
In ProgressDevices97
FAT Complete0/97
SAT Complete0/97
CBN Onboarded0/97
Security
In ProgressDevices2
FAT Complete0/2
SAT Complete0/2
CBN Onboarded0/2
Handover Documentation
Device Information Register (DIR)Required
CompletePoints RegisterRequired
Complete!
FAT CertificatesRequiredSAT CertificatesRequired
PendingNetwork DiagramsRequired
PendingSecurity Audit ReportRequired
PendingO&M ManualsRequired
PendingTraining Records
PendingAs-Built DrawingsRequired
PendingWarranty DocumentsRequired
Pending